Evaluating the impacts of using piles and geosynthetics in reducing the settlement of fine-grained soils under static load

Authors: 

Mahdi Shariati, Sadaf Mahmoudi Azar, Mohammad-Ali Arjomand, Hesam Salmani Tehrani,Mojtaba Daei, Maryam Safa

Source title: 
Geomechanics and Engineering, 20(2): 87-101, 2020 (ISI)
Academic year of acceptance: 
2020-2021
Abstract: 

The construction of combined pile-raft foundations is considered as the main option in designing foundations in high-rise buildings, especially in soils close to the ground surface which do not have sufficient bearing capacity to withstand building loads. This paper deals with the geotechnical report of the Northern Fereshteh area of Tabriz, Iran, and compares the characteristics of the single pile foundation with the two foundations of pile group and geogrid. Besides, we investigate the effects of five principal parameters including pile diameter and length, the number of geogrid layers, the depth of groundwater level, and pore water pressure on vertical consolidation settlement and pore water pressure changes over a year. This study assessed the mechanism of the failure of the soil under the foundation using numerical analysis as well. Numerical analysis was performed using the two-dimensional finite element PLAXIS software. The results of fifty-four models indicate that the diameter of the pile tip, either as a pile group or as a single pile, did not have a significant effect on the reduction of the consolidation settlement in the soil in the Northern Fereshteh Street region. The optimum length for the pile in the Northern Fereshteh area is 12 meters, which is economically feasible. In addition, the construction of four-layered ten-meter-long geogrids at intervals of 1 meter beneath the deep foundation had a significant preventive impact on the consolidation settlement in clayey soils.